County Road 43 - Widening Project
Schedule
The work for roadway construction began in March 2024 with the Bridge work beginning in July 2024. The work will be staged and span for approximately 3 years. The first year will include the preparation, mobilization, advance work, and installation of environmental protection measures.
How work is progressing in 2024
Excavations along North side of County Road 43
55%
Excavations along South side of County Road 43
0%
Installation of new underground utilities
13%